HierarchIndex |
Name |
Start |
End |
Duration |
1 |
Datacenter move |
Sun 2020-03-01 |
Fri 2020-10-30 |
243 |
2 |
Reduced capacity buildout |
Sun 2020-03-01 |
Fri 2020-06-12 |
103 |
3 |
Move 1: Essential hardware to IAD2 |
Mon 2020-04-13 |
Mon 2020-04-13 |
0 |
4 |
Move 2: Communishift to RDU-CC |
Mon 2020-04-13 |
Mon 2020-04-13 |
0 |
5 |
Move 3: QA equipment to IAD2 |
Mon 2020-04-13 |
Mon 2020-04-13 |
0 |
6 |
Communishift outage |
Mon 2020-04-13 |
Fri 2020-10-30 |
200 |
7 |
Moving services and applications to new DC |
Mon 2020-06-08 |
Fri 2020-06-12 |
4 |
8 |
Move 4: Remaining hardware to IAD2 |
Mon 2020-06-15 |
Mon 2020-06-15 |
0 |
9 |
Reduced capacity infrastructure |
Mon 2020-06-15 |
Fri 2020-07-10 |
25 |
10 |
Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) |
Wed 2020-06-24 |
Wed 2020-06-24 |
0 |
11 |
Compose tooling completed deadline |
Wed 2020-07-29 |
Wed 2020-07-29 |
0 |
12 |
Beta Freeze (starts at 1400 UTC) |
Tue 2020-08-25 |
Tue 2020-09-29 |
35 |
13 |
Beta Infrastructure Change Freeze |
Tue 2020-08-25 |
Tue 2020-09-29 |
35 |
14 |
Final Freeze (starts at 1400 UTC) |
Tue 2020-10-06 |
Tue 2020-10-27 |
21 |
15 |
Final Infrastructure Change Freeze |
Tue 2020-10-06 |
Tue 2020-10-27 |
21 |