| Key | Web | Development | Spins | Infrastructure | Quality | Project Leader | Elections | Upstream | RelEng | Mindshare | All Milestones | PgM | Marketing | Design | Translation | All | Docs | F30 | F29 |
| HierarchIndex | Name | Start | End | Duration |
|---|---|---|---|---|
| 1 | Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) | Wed 2019-06-26 | Wed 2019-06-26 | 0 |
| 2 | Compose tooling completed deadline | Wed 2019-07-31 | Wed 2019-07-31 | 0 |
| 3 | Beta Freeze | Tue 2019-08-27 | Tue 2019-09-17 | 21 |
| 4 | Beta Infrastructure Change Freeze | Tue 2019-08-27 | Tue 2019-09-17 | 21 |
| 5 | Final Freeze | Tue 2019-10-08 | Tue 2019-10-29 | 21 |
| 6 | Final Infrastructure Change Freeze | Tue 2019-10-08 | Tue 2019-10-29 | 21 |