HierarchIndex | Name | Start | End | Duration |
---|---|---|---|---|
1 | Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) | Wed 2019-06-26 | Wed 2019-06-26 | 0 |
2 | Compose tooling completed deadline | Wed 2019-07-31 | Wed 2019-07-31 | 0 |
3 | Beta Freeze | Tue 2019-08-27 | Tue 2019-09-17 | 21 |
4 | Beta Infrastructure Change Freeze | Tue 2019-08-27 | Tue 2019-09-17 | 21 |
5 | Final Freeze | Tue 2019-10-08 | Tue 2019-10-29 | 21 |
6 | Final Infrastructure Change Freeze | Tue 2019-10-08 | Tue 2019-10-29 | 21 |