| HierarchIndex |
Name |
Start |
End |
Duration |
| 1 |
Call for test days |
Tue 2019-05-28 |
Tue 2019-05-28 |
0 |
| 2 |
Create test days |
Tue 2019-06-11 |
Mon 2019-10-14 |
125 |
| 3 |
Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) |
Wed 2019-06-26 |
Wed 2019-06-26 |
0 |
| 4 |
Change Checkpoint: Proposal submission deadline (Changes requiring mass rebuild) |
Tue 2019-07-02 |
Tue 2019-07-02 |
0 |
| 5 |
Change Checkpoint: Proposal submission deadline (System Wide Changes) |
Tue 2019-07-02 |
Tue 2019-07-02 |
0 |
| 6 |
Branch Fedora 31 from Rawhide |
Tue 2019-08-13 |
Tue 2019-08-13 |
0 |
| 7 |
Bodhi activation point |
Tue 2019-08-27 |
Tue 2019-08-27 |
0 |
| 8 |
Beta Freeze |
Tue 2019-08-27 |
Tue 2019-09-17 |
21 |
| 9 |
"Common bugs" page to be created |
Tue 2019-08-27 |
Tue 2019-08-27 |
0 |
| 10 |
Beta Release Readiness Meeting |
Thu 2019-09-12 |
Thu 2019-09-12 |
0 |
| 11 |
Beta release Go/No-Go Meeting |
Thu 2019-09-12 |
Thu 2019-09-12 |
0 |
| 12 |
Beta Release Public Availability |
Tue 2019-09-17 |
Tue 2019-09-24 |
7 |
| 13 |
Beta Release (Preferred Target) |
Tue 2019-09-17 |
Tue 2019-09-17 |
0 |
| 14 |
Beta Target date #1 |
Tue 2019-09-24 |
Tue 2019-09-24 |
0 |
| 15 |
Final Freeze |
Tue 2019-10-08 |
Tue 2019-10-29 |
21 |
| 16 |
Final Release Readiness Meeting |
Thu 2019-10-17 |
Thu 2019-10-17 |
0 |
| 17 |
Final Release Public Availability (GA) |
Tue 2019-10-22 |
Tue 2019-10-29 |
7 |
| 18 |
Preferred Final Target date |
Tue 2019-10-22 |
Tue 2019-10-22 |
0 |
| 19 |
Final release Go/No-Go Meeting |
Thu 2019-10-24 |
Thu 2019-10-24 |
0 |
| 20 |
"Common bugs" page to be updated for final release |
Thu 2019-10-24 |
Thu 2019-10-24 |
0 |
| 21 |
Current Final Target date |
Tue 2019-10-29 |
Tue 2019-10-29 |
0 |
| 22 |
Final Target date #1 |
Tue 2019-10-29 |
Tue 2019-10-29 |
0 |
| 23 |
Blocker bug tracker update |
Tue 2019-10-29 |
Tue 2019-10-29 |
0 |