| HierarchIndex |
Name |
Start |
End |
Duration |
| 1 |
Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) |
Wed 2019-12-25 |
Wed 2019-12-25 |
0 |
| 2 |
Compose tooling completed deadline |
Mon 2020-02-03 |
Mon 2020-02-03 |
0 |
| 3 |
Beta Freeze (starts at 1400 UTC) |
Tue 2020-02-25 |
Tue 2020-03-17 |
21 |
| 4 |
Beta Infrastructure Change Freeze |
Tue 2020-02-25 |
Tue 2020-03-17 |
21 |
| 5 |
Datacenter move |
Fri 2020-02-28 |
Mon 2020-07-13 |
136 |
| 6 |
Old OpenStack instance retired |
Fri 2020-02-28 |
Fri 2020-02-28 |
0 |
| 7 |
Reduced capacity infra Buildout |
Sun 2020-03-01 |
Fri 2020-05-29 |
89 |
| 8 |
Final Freeze (starts at 1400 UTC) |
Thu 2020-04-09 |
Tue 2020-04-28 |
19 |
| 9 |
Final Infrastructure Change Freeze |
Thu 2020-04-09 |
Tue 2020-04-28 |
19 |
| 10 |
Move 1: Essential hardware to IAD2 |
Mon 2020-04-13 |
Mon 2020-04-13 |
0 |
| 11 |
Move 2: Communishift to RDU-CC |
Mon 2020-04-13 |
Mon 2020-04-13 |
0 |
| 12 |
Communishift outage |
Mon 2020-04-13 |
Fri 2020-06-26 |
74 |
| 13 |
Taskotron retirement |
Thu 2020-04-30 |
Thu 2020-04-30 |
0 |
| 14 |
Move 3: QA equipment to IAD2 |
Mon 2020-05-11 |
Mon 2020-05-11 |
0 |
| 15 |
Move 4: Remaining hardware to IAD2 |
Mon 2020-06-01 |
Mon 2020-06-01 |
0 |
| 16 |
Reduced capacity infrastructure |
Mon 2020-06-01 |
Mon 2020-07-13 |
42 |