HierarchIndex |
Name |
Start |
End |
Duration |
1 |
Call for test days |
Tue 2019-11-19 |
Tue 2019-11-19 |
0 |
2 |
Create test days |
Tue 2019-12-10 |
Mon 2020-04-13 |
125 |
3 |
Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) |
Wed 2019-12-25 |
Wed 2019-12-25 |
0 |
4 |
Change Checkpoint: Proposal submission deadline (Changes requiring mass rebuild) |
Tue 2019-12-31 |
Tue 2019-12-31 |
0 |
5 |
Change Checkpoint: Proposal submission deadline (System Wide Changes) |
Tue 2019-12-31 |
Tue 2019-12-31 |
0 |
6 |
Branch Fedora 32 from Rawhide |
Tue 2020-02-11 |
Tue 2020-02-11 |
0 |
7 |
Bodhi updates-testing activation point |
Tue 2020-02-25 |
Tue 2020-02-25 |
0 |
8 |
Beta Freeze (starts at 1400 UTC) |
Tue 2020-02-25 |
Tue 2020-03-17 |
21 |
9 |
"Common bugs" page to be created |
Tue 2020-02-25 |
Tue 2020-02-25 |
0 |
10 |
Beta Release Readiness Meeting |
Thu 2020-03-12 |
Thu 2020-03-12 |
0 |
11 |
Beta release Go/No-Go Meeting |
Thu 2020-03-12 |
Thu 2020-03-12 |
0 |
12 |
Beta Release Public Availability |
Tue 2020-03-17 |
Tue 2020-03-24 |
7 |
13 |
Beta Release (Preferred Target) |
Tue 2020-03-17 |
Tue 2020-03-17 |
0 |
14 |
Current Beta Target date |
Tue 2020-03-17 |
Tue 2020-03-17 |
0 |
15 |
Beta Target date #1 |
Tue 2020-03-24 |
Tue 2020-03-24 |
0 |
16 |
Final Freeze (starts at 1400 UTC) |
Thu 2020-04-09 |
Tue 2020-04-28 |
19 |
17 |
Final Release Readiness Meeting |
Thu 2020-04-16 |
Thu 2020-04-16 |
0 |
18 |
Final Release Public Availability (GA) |
Tue 2020-04-21 |
Tue 2020-04-28 |
7 |
19 |
Preferred Final Target date |
Tue 2020-04-21 |
Tue 2020-04-21 |
0 |
20 |
Final release Go/No-Go Meeting |
Thu 2020-04-23 |
Thu 2020-04-23 |
0 |
21 |
"Common bugs" page to be updated for final release |
Thu 2020-04-23 |
Thu 2020-04-23 |
0 |
22 |
Current Final Target date |
Tue 2020-04-28 |
Tue 2020-04-28 |
0 |
23 |
Final Target date #1 |
Tue 2020-04-28 |
Tue 2020-04-28 |
0 |
24 |
Blocker bug tracker update |
Tue 2020-04-28 |
Tue 2020-04-28 |
0 |