Fedora Linux 48 Schedule: RelEng

HierarchIndex Name Start End Duration
1 Rawhide starts Fedora Linux 48 development Tue 2026-08-11 Tue 2026-08-11 0
2 Notifications for retirement of packages with security issues Tue 2027-06-01 Mon 2027-06-28 27
3 Retire packages with security issues Mon 2027-06-28 Mon 2027-06-28 0
4 Begin reminders for packages that haven't rebuilt in last 2 releases
https://docs.fedoraproject.org/en-US/fesco/Fails_to_build_from_source_Fails_to_install/
Tue 2027-06-29 Tue 2027-06-29 0
5 Change Checkpoint: Major Toolchain Updates/Changes have landed in Rawhide deadline Mon 2027-07-12 Mon 2027-07-12 0
6 Mass Rebuild: RPMs
https://docs.fedoraproject.org/en-US/infra/release_guide/mass_rebuild/
Wed 2027-07-14 Tue 2027-08-10 27
7 F50 keys are added to fedora-repos and are available in updates-testing
https://docs.fedoraproject.org/en-US/infra/release_guide/create_release_signing_key/
Tue 2027-07-27 Tue 2027-07-27 0
8 Re-sign F47 content with F48 Tue 2027-08-03 Tue 2027-08-03 0
9 Retire Orphaned and Long-Time FTBFS Rawhide Packages
https://docs.fedoraproject.org/en-US/fesco/Fails_to_build_from_source_Fails_to_install/
Tue 2027-08-03 Tue 2027-08-03 0
10 Branch Fedora Linux 48 from Rawhide Tue 2027-08-10 Tue 2027-08-10 0
11 Rawhide starts Fedora Linux 49 development Tue 2027-08-10 Tue 2027-08-10 0
12 Update Greenwave policy product_versions to add branched release Tue 2027-08-10 Tue 2027-08-10 0
13 Post-branch Freeze (end date approximate) Tue 2027-08-10 Fri 2027-08-13 3
14 File FTBFS bugs from mass rebuild Tue 2027-08-10 Tue 2027-08-10 0
15 Retire FTI packages in NEW state
https://docs.fedoraproject.org/en-US/fesco/Fails_to_build_from_source_Fails_to_install/
Tue 2027-08-17 Tue 2027-08-17 0
16 Bodhi updates-testing activation point Tue 2027-08-24 Tue 2027-08-24 0
17 Beta Freeze (starts at 1400 UTC) Tue 2027-08-24 Tue 2027-09-14 21
18 Beta release Go/No-Go Meeting
https://fedoraproject.org/wiki/Go_No_Go_Meeting
Thu 2027-09-09 Thu 2027-09-09 0
19 Stage Beta on master minor Thu 2027-09-09 Mon 2027-09-13 4
20 Notify Mirrors of Beta Release Thu 2027-09-09 Thu 2027-09-09 0
21 Bit-flip Beta to mirrors Mon 2027-09-13 Mon 2027-09-13 0
22 Beta Release (Early Target)
Fedora contributors plan on this
Tue 2027-09-14 Tue 2027-09-14 0
23 Current Beta Target date
https://docs.fedoraproject.org/en-US/releases/lifecycle/#_release_dates
Tue 2027-09-14 Tue 2027-09-14 0
24 Beta Target date #1
Fedora users plan on this
Tue 2027-09-21 Tue 2027-09-21 0
25 Retire FTI packages in NEW state
https://docs.fedoraproject.org/en-US/fesco/Fails_to_build_from_source_Fails_to_install/
Tue 2027-09-28 Tue 2027-09-28 0
26 Final Freeze (starts at 1400 UTC) Tue 2027-10-05 Tue 2027-10-19 14
27 Retire all packages with broken deps Tue 2027-10-05 Tue 2027-10-05 0
28 Enable Updates in Bodhi for the current release Wed 2027-10-13 Wed 2027-10-13 0
29 Final release Go/No-Go Meeting
https://fedoraproject.org/wiki/Go_No_Go_Meeting
Thu 2027-10-14 Thu 2027-10-14 0
30 Stage Final on master minor Thu 2027-10-14 Mon 2027-10-18 4
31 Notify Mirrors of Final Release Thu 2027-10-14 Thu 2027-10-14 0
32 Bit-flip Final to mirrors Mon 2027-10-18 Mon 2027-10-18 0
33 Current Final Target date
Fedora users plan on this
Tue 2027-10-19 Tue 2027-10-19 0
34 Early Final Target date
https://docs.fedoraproject.org/en-US/releases/lifecycle/#_release_dates
Tue 2027-10-19 Tue 2027-10-19 0
35 Set current release to active in Package database Tue 2027-10-19 Tue 2027-10-19 0
36 Post Release Cleanup [rel-eng] Wed 2027-10-20 Wed 2027-10-27 7
37 Final Target date #1
Fedora contributors plan on this
Tue 2027-10-26 Tue 2027-10-26 0
38 REMINDER: EOL release final update push in 1 week Wed 2027-11-10 Wed 2027-11-10 0
39 REMINDER: EOL release final update push in 1 day Tue 2027-11-16 Tue 2027-11-16 0
40 Fedora Linux 46 EOL auto closure Wed 2027-11-17 Wed 2027-11-17 0
41 Update Greenwave policy product_versions to remove EOL release Wed 2027-11-17 Wed 2027-11-17 0
42 Remove Beta images Wed 2027-11-17 Wed 2027-11-17 0
43 Remove F46 from Greenwave Wed 2027-11-17 Wed 2027-11-17 0
44 Fedora Linux 48 End of Life
This is a changeable date and currently based off the Early Target Date
Wed 2028-11-22 Wed 2028-11-22 0