Fedora 23 |
Tue 2015-04-21 |
Tue 2015-12-15 |
238.8 |
Testing Phase |
Tue 2015-04-21 |
Tue 2015-10-27 |
189.8 |
Alpha Release |
Tue 2015-04-21 |
Tue 2015-09-15 |
147.8 |
Change Checkpoint: Proposal submission deadline (System Wide Changes) |
Tue 2015-06-23 |
Tue 2015-06-23 |
0 |
Custom Spins Submission Deadline |
Tue 2015-06-23 |
Tue 2015-06-23 |
0 |
Change Checkpoint: Completion deadline (testable) |
Tue 2015-07-14 |
Tue 2015-07-14 |
0 |
Spins Freeze--All Fedora 23 Spins Identified |
Tue 2015-07-14 |
Tue 2015-07-14 |
0 |
Branch Fedora 23 from Rawhide |
Tue 2015-07-14 |
Tue 2015-07-14 |
0 |
Alpha Release Public Availability |
Tue 2015-08-11 |
Tue 2015-08-11 |
0 |
Beta Release |
Tue 2015-04-21 |
Mon 2015-10-12 |
174.8 |
Change Checkpoint: 100% Code Complete Deadline |
Tue 2015-09-08 |
Tue 2015-09-08 |
0 |
Beta Release Public Availability |
Tue 2015-09-22 |
Tue 2015-09-22 |
0 |
Launch Phase |
Tue 2015-04-21 |
Tue 2015-12-15 |
238.8 |
Final Release Public Availability (GA) |
Tue 2015-11-03 |
Tue 2015-11-03 |
0 |
Public Relations |
Tue 2015-08-11 |
Wed 2015-11-04 |
85.4 |
Creative team videos |
Tue 2015-08-11 |
Tue 2015-11-03 |
84.4 |
Meet w/Creative to schedule videos |
Tue 2015-08-11 |
Tue 2015-08-18 |
7 |
Make spotlight video #1 |
Tue 2015-09-22 |
Tue 2015-10-13 |
21 |
Review video #1 |
Tue 2015-09-22 |
Tue 2015-10-13 |
21 |
Publish spotlight video #1 |
Tue 2015-10-13 |
Tue 2015-10-13 |
0 |
Make spotlight video #2 |
Tue 2015-10-06 |
Tue 2015-10-27 |
21 |
Review video #2 |
Tue 2015-10-06 |
Tue 2015-10-27 |
21 |
Publish spotlight video #2 |
Tue 2015-10-27 |
Tue 2015-10-27 |
0 |
Make release video |
Wed 2015-10-07 |
Tue 2015-11-03 |
27.3 |
Review release video |
Wed 2015-10-07 |
Tue 2015-11-03 |
27.3 |
Publish release video |
Tue 2015-11-03 |
Tue 2015-11-03 |
0 |
Beta press blog entry |
Tue 2015-08-25 |
Tue 2015-09-22 |
28.3 |
Start drafting Beta blog |
Tue 2015-08-25 |
Tue 2015-09-08 |
14 |
Red Hat PR send Beta blog to Legal |
Tue 2015-09-08 |
Tue 2015-09-15 |
7 |
Red Hat PR send Beta blog to intl-pr list |
Tue 2015-09-15 |
Tue 2015-09-22 |
7.4 |
Red Hat PR publish and send Beta blog to media contacts |
Tue 2015-09-22 |
Tue 2015-09-22 |
0 |
Update Red Hat web site |
Tue 2015-09-22 |
Tue 2015-11-03 |
42.3 |
Schedule meeting with Red Hat web team to plan launch |
Tue 2015-09-22 |
Tue 2015-09-29 |
7 |
Send web promo ideas to Brand |
Tue 2015-09-29 |
Tue 2015-10-06 |
7 |
Review and update www.redhat.com/Fedora copy |
Tue 2015-10-06 |
Tue 2015-10-13 |
7 |
Send updated copy to Web team |
Tue 2015-10-13 |
Tue 2015-10-20 |
7 |
Red Hat website changes go live |
Tue 2015-11-03 |
Tue 2015-11-03 |
0 |
USB Keys and media pre-briefs |
Thu 2015-09-24 |
Tue 2015-11-03 |
40.3 |
Purchase USB Keys |
Thu 2015-09-24 |
Thu 2015-10-01 |
7 |
Check LiveUSB press review sheet for readiness |
Thu 2015-09-24 |
Thu 2015-10-01 |
7 |
Update LiveUSB press review sheet |
Thu 2015-10-01 |
Thu 2015-10-08 |
7 |
Prep USB keys with pre-release |
Thu 2015-10-01 |
Thu 2015-10-08 |
7 |
Send USB keys to Red Hat PR for distribution |
Thu 2015-10-08 |
Tue 2015-10-13 |
5 |
Red Hat PR distribute USB keys to media contacts |
Fri 2015-10-09 |
Fri 2015-10-16 |
7 |
Hold media prebrief interviews |
Tue 2015-10-27 |
Tue 2015-11-03 |
7.4 |
Spotlight feature press blogs |
Tue 2015-09-29 |
Tue 2015-10-27 |
28 |
Spotlight feature #1 |
Tue 2015-09-29 |
Tue 2015-10-13 |
14 |
Draft spotlight #1 blog entry |
Tue 2015-09-29 |
Tue 2015-10-06 |
7 |
Red Hat PR send spotlight #1 blog entry draft to legal |
Tue 2015-10-06 |
Tue 2015-10-13 |
7 |
Red Hat PR publish spotlight #1 blog entry |
Tue 2015-10-13 |
Tue 2015-10-13 |
0 |
Spotlight feature #2 |
Tue 2015-10-06 |
Tue 2015-10-20 |
14 |
Draft spotlight #2 blog entry |
Tue 2015-10-06 |
Tue 2015-10-13 |
7 |
Red Hat PR send spotlight #2 blog entry draft to legal |
Tue 2015-10-13 |
Tue 2015-10-20 |
7 |
Red Hat PR publish spotlight #2 blog entry |
Tue 2015-10-20 |
Tue 2015-10-20 |
0 |
Spotlight feature #3 |
Tue 2015-10-13 |
Tue 2015-10-27 |
14 |
Draft spotlight #3 blog entry |
Tue 2015-10-13 |
Tue 2015-10-20 |
7 |
Red Hat PR send spotlight #3 blog entry draft to legal |
Tue 2015-10-20 |
Tue 2015-10-27 |
7 |
Red Hat PR publish spotlight #3 blog entry |
Tue 2015-10-27 |
Tue 2015-10-27 |
0 |
GA press release |
Tue 2015-10-06 |
Tue 2015-11-03 |
28.3 |
Start drafting GA press release |
Tue 2015-10-06 |
Tue 2015-10-20 |
14 |
Red Hat PR send GA press release to Legal |
Tue 2015-10-20 |
Tue 2015-10-27 |
7 |
Red Hat PR send GA press release to intl-pr list |
Tue 2015-10-27 |
Tue 2015-11-03 |
7.4 |
Red Hat PR publish and send GA press release to media contacts |
Tue 2015-11-03 |
Tue 2015-11-03 |
0 |
CEO press blog entry |
Fri 2015-10-16 |
Wed 2015-11-04 |
19.3 |
Prepare a final RC on USB for CEO |
Fri 2015-10-16 |
Tue 2015-10-20 |
4 |
Send final RC USB key to CEO |
Tue 2015-10-20 |
Thu 2015-10-22 |
2 |
Solicit CEO feedback on pre-release |
Thu 2015-10-22 |
Wed 2015-10-28 |
6 |
Draft CEO blog |
Wed 2015-10-28 |
Mon 2015-11-02 |
5 |
Red Hat PR send CEO blog to Legal |
Mon 2015-11-02 |
Wed 2015-11-04 |
2.3 |
Red Hat PR publish and send CEO blog to media contacts |
Wed 2015-11-04 |
Wed 2015-11-04 |
0 |