No. | Name | Start | End | Duration |
1. | Packaging and Development (precedes Alpha) | Wed 2013-04-17 | Tue 2013-09-03 | 139.8 |
2. | Change Proposals Submission Deadline | Tue 2013-07-30 | Tue 2013-07-30 | 0 |
3. | Custom Spins Submission Deadline | Tue 2013-07-30 | Tue 2013-07-30 | 0 |
4. | Change Proposals Freeze (Testable|Complete) | Tue 2013-08-20 | Tue 2013-08-20 | 0 |
5. | Spins Freeze--All Fedora 20 Spins Identified | Tue 2013-08-20 | Tue 2013-08-20 | 0 |
6. | Branch Fedora 20 from Rawhide | Tue 2013-08-20 | Tue 2013-08-20 | 0 |
7. | Create First Alpha Test Compose (TC1) | Tue 2013-08-20 | Tue 2013-08-20 | 0 |
8. | Test Alpha 'Test Compose' | Tue 2013-08-20 | Thu 2013-09-12 | 23 |
9. | Alpha Change Deadline | Tue 2013-09-03 | Tue 2013-09-03 | 0 |
10. | Software String Freeze | Tue 2013-09-03 | Tue 2013-09-03 | 0 |
11. | Fedora 20 Alpha Go/No-Go Meeting (17:00 US Eastern) | Thu 2013-09-19 | Thu 2013-09-19 | 0 |
12. | Stage & Sync Alpha to Mirrors | Thu 2013-09-19 | Tue 2013-09-24 | 5 |
13. | Alpha Release Public Availability | Tue 2013-09-24 | Tue 2013-09-24 | 0 |
14. | Alpha Testing | Tue 2013-09-24 | Tue 2013-10-15 | 21 |
15. | Create First Beta Test Compose (TC1) | Tue 2013-10-01 | Tue 2013-10-01 | 0 |
16. | Test Beta 'Test Compose' | Tue 2013-10-01 | Thu 2013-10-24 | 23 |
17. | Beta Change Deadline | Tue 2013-10-15 | Tue 2013-10-15 | 0 |
18. | Changes 100% Complete Deadline | Tue 2013-10-15 | Tue 2013-10-15 | 0 |
19. | Fedora 20 Beta Go/No-Go Meeting (17:00 US Eastern) | Thu 2013-11-07 | Thu 2013-11-07 | 0 |
20. | Stage & Sync Beta to Mirrors | Thu 2013-11-07 | Tue 2013-11-12 | 5 |
21. | Beta Release Public Availability | Tue 2013-11-12 | Tue 2013-11-12 | 0 |
22. | Create First 'Final' Test Compose (TC1) | Tue 2013-11-12 | Tue 2013-11-12 | 0 |
23. | Test 'Final' Test Compose (TC) | Tue 2013-11-12 | Mon 2013-11-18 | 6 |
24. | Beta Testing | Tue 2013-11-12 | Mon 2013-11-25 | 13 |
25. | Final Change Deadline | Tue 2013-11-26 | Tue 2013-11-26 | 0 |
26. | Fedora 20 Final Go/No-Go Meeting (17:00 US Eeastern) | Thu 2013-12-12 | Thu 2013-12-12 | 0 |
27. | Stage & Sync RC to Mirrors | Thu 2013-12-12 | Tue 2013-12-17 | 5 |
28. | Final Release Public Availability (GA) | Tue 2013-12-17 | Tue 2013-12-17 | 0 |
Version 20 - Created on 2016-Sep-05 with TaskJuggler v2.4.3