No. | Name | Start | End | Duration |
1. | Packaging and Development (precedes Alpha) | Wed 2012-11-28 | Tue 2013-04-02 | 125.7 |
2. | Feature Submission Deadline | Tue 2013-01-22 | Tue 2013-01-22 | 0 |
3. | Custom Spins Submission Deadline | Tue 2013-01-22 | Tue 2013-01-22 | 0 |
4. | Feature Freeze (Testable|Complete) | Tue 2013-03-12 | Tue 2013-03-12 | 0 |
5. | Spins Freeze--All Fedora 19 Spins Identified | Tue 2013-03-12 | Tue 2013-03-12 | 0 |
6. | Branch Fedora 19 from Rawhide | Tue 2013-03-12 | Tue 2013-03-12 | 0 |
7. | Create First Alpha Test Compose (TC1) | Tue 2013-03-19 | Tue 2013-03-19 | 0 |
8. | Software String Freeze | Tue 2013-03-19 | Tue 2013-03-19 | 0 |
9. | Test Alpha 'Test Compose' | Tue 2013-03-19 | Thu 2013-04-11 | 23 |
10. | Alpha Change Deadline | Tue 2013-04-02 | Tue 2013-04-02 | 0 |
11. | Fedora 19 Alpha Go/No-Go Meeting (17:00 US Eastern) | Thu 2013-04-18 | Thu 2013-04-18 | 0 |
12. | Stage & Sync Alpha to Mirrors | Thu 2013-04-18 | Tue 2013-04-23 | 5 |
13. | Alpha Release Public Availability | Tue 2013-04-23 | Tue 2013-04-23 | 0 |
14. | Alpha Testing | Tue 2013-04-23 | Tue 2013-05-14 | 21 |
15. | Create First Beta Test Compose (TC1) | Tue 2013-04-30 | Tue 2013-04-30 | 0 |
16. | Test Beta 'Test Compose' | Tue 2013-04-30 | Thu 2013-05-23 | 23 |
17. | Beta Change Deadline | Tue 2013-05-14 | Tue 2013-05-14 | 0 |
18. | Features 100% Complete Deadline | Tue 2013-05-14 | Tue 2013-05-14 | 0 |
19. | Fedora 19 Beta Go/No-Go Meeting (17:00 US Eastern) | Thu 2013-05-23 | Thu 2013-05-23 | 0 |
20. | Stage & Sync Beta to Mirrors | Thu 2013-05-23 | Tue 2013-05-28 | 5 |
21. | Beta Release Public Availability | Tue 2013-05-28 | Tue 2013-05-28 | 0 |
22. | Beta Testing | Tue 2013-05-28 | Mon 2013-06-17 | 20 |
23. | Create First 'Final' Test Compose (TC1) | Tue 2013-06-04 | Tue 2013-06-04 | 0 |
24. | Test 'Final' Test Compose (TC) | Tue 2013-06-04 | Mon 2013-06-10 | 6 |
25. | Final Change Deadline | Tue 2013-06-18 | Tue 2013-06-18 | 0 |
26. | Fedora 19 Final Go/No-Go Meeting (17:00 US Eeastern) | Thu 2013-06-27 | Thu 2013-06-27 | 0 |
27. | Stage & Sync RC to Mirrors | Thu 2013-06-27 | Tue 2013-07-02 | 5 |
28. | Final Release Public Availability (GA) | Tue 2013-07-02 | Tue 2013-07-02 | 0 |
Version 19 - Created on 2016-Sep-05 with TaskJuggler v2.4.3